Home Past Events Forthcoming Events Case Studies In the Press      
 

CASE STUDIES

Guru Gobind Singh (Bhatinda) Refinery
Concept to commissioning – a twelve year long journey


The twelve year journey of Guru Gobind Singh Refinery from early 2000, when HPCL announced its intention to set up a green field refinery in Punjab to 28 April 2012, when Dr Manmohan Singh, Prime Minister of India, dedicated the project to the nation, was a bit long by any yardstick for a 9 million tonne refinery.

The project involved construction of 9 million tonne refinery, crude oil storage tanks, a pipeline between Mundra and Bhatinda and 250 km pipeline between Bhatinda and Pathankot.

HPCL proposed to set up the green field refinery originally in early 2000 with Aramco of Saudi Arabia. When Aramco discontinued its association with the project, HPCL roped in Exxon Corpn of the USA. Later in early 1999, Exxon also withdrew from the project believing that following the plans of Reliance and Essar Oil to expand their refining capacities, the viablity of HPCL refinery looks dim. Citing the same reasons, ONGC also refused to partner with HPCL. The agreement signed with British Petrolem in Oct 2005 fell apart as BP also withdrew from the project.

HPCL started ground work on the refinery in early 2000. By August 2006, the project cost jumped up from 9,082 crore to Rs 15,072 crore. In March 2007, L N Mittal signed an MoU with Hindustan Petroleum Corporation for equity partnership hold a 49 per cent stake, while HPCL hold 49 per cent stake and remaining two per cent will be held by financial institutions.

"HPCL Mittal Energy Ltd. (HMEL) is a good platform to grow (in energy space)," Mittal said at the time of inauguration. He further added that "I am not ready for my guys to think loud" before the refinery stabilises in a year’s time. Adding a low-cost expansion of existing units to raise refining capacity to 11.2 million tonnes would be considered after that.”

Bandra – Worli Sea Link
An engineering marvel built with 5 years delay and 430% hike in cost!

Seshadri Srinivasan with his design of the Sea Link Bandra-Worli Sea Link

While China completed seven sea-links in six years, it took India 10 years to complete its first sea-link project in Mumbai. Nevertheless, it is considered as one of the engineering marvels of post-independence era.

The 5.6 km long sea link project was commissioned by the Maharashtra State Road Development Corporation Limited (MSRDC) and the EPC contract was executed by the Hindustan Construction Company (HCC), with project management led by Dar Al-Handasah, UK. The foundation stone was laid by Bal Thackeray, the Shiv Sena chief in 1999. When the construction began in 2000, the bridge was expected to be completed by 2005 at a cost of Rs 300 crore. However, when fully completed in March 2010, the project saw a time over run of 5 years and a cost over-run of a whopping 430 per cent (from Rs 300 crore to Rs 1600 crore).

Plagued by a series of public interest litigations from fishermen and environmentalists, the work on the project could not take off till October 2004. The agitations also forced MSRDC to make drastic changes in the design of the bridge.

The Sea Link, also known as the Rajiv Gandhi Sea Link, is a cable-stayed bridge with pre-stressed concrete-steel viaducts on either side. While the first four of the eight lanes of the bridge were opened to the public on 30 June 2009, the balance four lanes were opened on 24 March 2010. The bridge reduces travel time between Bandra and Worli during peak hours from 60–90 minutes to around seven minutes.

The sea link was designed as the first cable-stayed bridge to be constructed in open seas in India. The superstructure of the viaducts were the heaviest precast segments to be built in India. The foundations for the cable-stayed bridges consist of 120 reinforced concrete piles of 6.6 feet diameter. Those for the viaducts consist of 484 piles of 4.9 feet.

The credit for designing the Bandra-Worli Sea link is ascribed to Seshadri Srinivasan, a bridge designer in the UK based consultant firm, Dar Al-Handsah. Srinivasan is credited with the design of the JJ Flyover in Mumbai.

Srinivasan mentioned that “Initially, it was a single tower, which would carry both decks on a single support. Then, when plans changed to the present-day two towers, the design got simplified. But this meant more expenditure, resources and spending more time on the project.”

 
Aconex Eril Executive Seminar
Past Events
  Delhi
ProjectsToday holds two-day executive Masterclass on ‘Doing Projects Right Today'
  Bengaluru
ProjectsToday holds two-day executive Masterclass on ‘Doing Projects Right Today'
Events Photo Gallery
 
 
Past Events Video
  Executive Master Class
ProjectsToday holds two-day executive Masterclass on ‘Doing Projects Right Today'
  Executive Master Class
ProjectsToday holds two-day executive Masterclass on ‘Doing Projects Right Today'
Official Publication
PR Partner
Telecast Partner
Consulting Partner
Supporting Organization

Consulting Enginneers
Association of India

Online Partner
 
Publication Partner
 

  © 2012 ERIL Events. All Rights Reserved. Economic Resarch India Pvt Ltd.